Overview
Before
- Grade 2 listed mid 19th century stucco fronted London town house that was partly damaged by a fire in 2012.
- It is now part of the Westbourne Hyde Park hotel complex, along with 7 other properties along the terrace.
After
JE Putney and Sons were awarded the contract to carry out the internal lime plaster repairs throughout the building including the renewal of all ceilings using new chestnut riven laths and 3 coat haired non-hydraulic lime plaster. The same materials were used on extensive internal partition walls throughout. J E Putney and Sons also carried out all the new ornate fibrous cornice works throughout.